Project Overview
As part of an existing service contract with our amazing partners at Liberty Lake Sewer & Water, B&E was tasked to replace an existing lift station that was in desperate need of being swapped out. To make the situation a little more challenging, the lift station had been backed into by a vehicle at some point.
Liberty Lake Lift Station Upgrade
1) Partnered with the local utility company to reconfigure power delivery
2) Designed and built a new Control Panel that included Telemetry, SCADA, Motor Controls, and Power Delivery
3) Removed existing control panel and installed our new panel.